Details About Slurry Engineering’s Projects Salinas River Diversion Facility CB Cut-Off Wall across Salinas River, Marina, CA Installation of a High Strength CB Cut-Off Wall across the Salinas River as a foundation support for an inflatable dam Approximate Depths of 50 feet, length of 400 feet. High groundwater conditions. Multiple elevation changes Tight schedule with multiple simultaneous operations Strength requirement of 300 psi in 28 days Installation of H-Beams into alignment of wall Average Strength Result of 535 psi in 28 day Installation of a High Strength CB Cut-Off Wall across the Salinas River as a foundation support for an inflatable dam Approximate Depths of 50 feet, length of 400 feet. High groundwater conditions. Multiple elevation changes Tight schedule with multiple simultaneous operations Strength requirement of 300 psi in 28 days Installation of H-Beams into alignment of wall Average Strength Result of 535 psi in 28 day Diavik Diamond Mine Plastic Concrete Cut-Off Wall in constructed dikes Lac de Gras, Northwest Territory, Canada Excavation under bentonite slurry by hydraulic clamshell and hydromill along dike alignment Slurry Pipeline to and from excavations Bentonite Hydration and Recycle Pond Clamshell excavation of panel under bentonite slurry Desanding Plant for Hydromill bentonite slurry recycling Open pit excavation, where a lake once was San Andreas Reservoir Cement-Bentonite annular fill for pipeline replacement at 70 feet water depth Pumping through 2-inch hose to submerged structure Mixing bentonite slurry, adding slag cement Transfer mix to agitator holding tank